Requirements Engineering/het werk/werkstuk/2008-9/Groep 02 Spectrometer/Organisatorisch

Uit Werkplaats
Ga naar: navigatie, zoeken

Op deze pagina staan alle organisatorische aspecten van het requirements traject van groep 2. Het resultaat is hier zichtbaar.

Planning

Legenda

Naam Representatie in planning
Niels Braakensiek N
Els van Dijk E
Roy de Vries R

Facade

Deadline: 27 oktober 2008

Deliverable Status in facade iteratie Uitvoerende
Introduction Preliminary version E
Problem statement As good as possible E
Stakeholder analysis As good as possible R
Mission-vision-values Complete E
Statement of work Complete, and up-to-date R
Risk analysis Complete, and up-to-date E
Use case survery As good as possible N
Use case diagram(s) As good as possible R
Integrated UC diagram Complete (though preliminary) R
Use cases Not yet! n.v.t.
Scenarios Not yet! n.v.t.
Domain models Not yet! n.v.t.
Integrated domain model Not yet! n.v.t.
Business rules catalogue Not yet! n.v.t.
Non-functional requirements Notes N - R - E
Terminological definitions Notes N - R - E
Executive sponsor viewpoint Complete (integrated in M-V-V!) zie M-V-(V)
Use case tests Notes N - R - E

Filled

Deadline: 3 december 2008

Deliverable Status in facade iteratie Uitvoerende
Introduction Preliminary version E
Problem statement As good as possible E
Stakeholder analysis As good as possible R
Mission-vision-values Complete E
Statement of work Complete, and up-to-date R
Risk analysis Complete, and up-to-date E - R
Use case survery Nearly complete N
Use case diagram(s) Nearly complete N - R - E
Integrated UC diagram Complete R
Use cases "Filled" level N - R - E
Scenarios Several for each UC N - R - E
Domain models Partially complete N - R - E
Integrated domain model Partially complete N
Business rules catalogue Partially complete N - R - E
Non-functional requirements Partially complete R - E
Terminological definitions Partially complete N - R - E
Executive sponsor viewpoint Complete (integrated in M-V-V!) zie M-V-(V)
Use case tests As good as possible n.v.t.

Focused

Deadline: 5 januari 2009

Deliverable Status in facade iteratie Uitvoerende
Introduction Complete E
Problem statement Complete E
Stakeholder analysis Complete R
Mission-vision-values Complete E
Statement of work Complete, and up-to-date R
Risk analysis Complete, and up-to-date E
Use case survery Complete N
Use case diagram(s) Complete R
Integrated UC diagram Complete R
Use cases Complete N - R - E
Scenarios Complete ("focused" level) N - R - E
Domain models Complete N - R - E
Integrated domain model Complete N
Business rules catalogue Complete N - R - E
Non-functional requirements Complete N - R - E
Terminological definitions Complete N - R - E
Executive sponsor viewpoint Complete (integrated in M-V-V!) zie M-V-(V)
Use case tests Complete N - R - E